Restaurant Re-fits

01/2018

Contract Value

£400K

Location

Gunwharf, Hampshire

Key Features

Pure Construction and Brymor Special Works Limited recently completed a restaurant strip-out and re-fit for Gunwharf Quays.

Part of a £1.8M refurbishment, Pure took on a £400K project that required them to strip out 2 existing restaurants and convert the building to accommodate 4 new ones. Work included:

  1. Partitioning
  2. Internal Tanking
  3. External Tanking
  4. Diamond Drilling
  5. Sika Roof
  6. Flashings
  7. Dibond Graphics
  8. Brickwork / Blockwork
  9. Specialist Stonework
  10. Screeding
  11. Concrete Floors
  12. Decorating

Fire Restoration

02/2017

Contract Value

circa. £1M

Location

Gunwharf, Hampshire

Key Features

Almost a year ago to the day, fire swept through the Roundhouse at Gunwharf, leaving 30 our of 50 flats completely destroyed. Smoke and water damage left the rest of the building in a dangerous state, resulting in an entire evacuation with most residents unable to return to their home.

Pictures depicting the devastating effects can be viewed at the following ITV article: Fire at Block of Flats, Meridian

Working with Brymor Construction, Pure Construction took immediate action after being contacted by the Gunwharf Management team. After carrying out extensive safety testing, the Pure team were able to get 43/50 residents back in to their home in under 12 days.

On-going work included a re-build of x1 flat in its entirety, followed by extensive work to x11 flats:

  1. Specialist injection drying
  2. Structural concrete repairs
  3. Electrical / Mechanical repairs
  4. Decorating
  5. Floor Installation
  6. Partitions
  7. Plastering
  8. Kitchen Installation
  9. Bathroom Installation
  10. External Cladding
  11. Sto Render
  12. Scaffolding
  13. Balcony Removal / Re-instatement
  14. Schcuo Doors and Frames
  15. Fire Doors replaced

Mountjoy Office Re-fit

Contract Value

Approx. £50K

Location

Portsmouth, Hampshire

Key Features

Mountjoy enlisted Pure Construction to complete an office fit-out at their Head Office in Portsmouth. The project included:

  1. Complete strip out
  2. Mechanical and Electrical services
  3. Suspended ceilings
  4. Partitions
  5. Plastering
  6. Decoration
“We are really happy with the job, so please forward our thanks to the team.” – Duncan O’Rourke, Project Manager, Mountjoy

West Quay Car Park

Contract Value

Approx. £100K

Location

Southampton, Hampshire

Key Features

Working in partnership with Brymor Specialist Works, Pure Construction undertook this project on behalf of West Quay Shopping Centre who are based in the heart of Southampton.  Over 12 weeks the two companies worked together to successfully;

  1. Re-line the multi-storey car park, levels 1-7
  2. Refurbish Fire Doors
  3. Decorate Stair Cores

Access Steps for Wickes

Contract Value

Approx. £50K

Location

Hedge End, Southampton

Key Features

Over a short period of just 6 weeks, Pure constructed Access Steps for household DIY store Wickes, in Hedge End, Southampton. The project included:

  1. Frame created from timber
  2. Installation of steelwork
  3. Concrete overlay
  4. Installation of cycle access
  5. Finished with slabs to cover the steps
  6. Installation of steel handrail